Huntington Middle School: The Next Chapter
The proud history of Huntington High School and Huntington Middle School will continue with the construction of a new 600-student middle school, anticipated to open during the 2026-2027 school year.
The new middle school is part of the city’s Southeast Community Resource Area that is set to include a public library and community center, as well as sports and recreation features.
Construction Progress Update
September 16, 2025
The Huntington Middle School building site is divided into four (4) building zones, A, B, C, and D. MEB General Contractors, Inc, the Contractor, is developing the building pad in the order of zones C, D, B, and A. The work completed in these building zones are as follows:

Zone “C”
- Roofing is complete for the gym.
- Roofing on remainder of C area low roof(s), i.e., entry way, staff dining, locker rooms, main corridor are approximately 25% complete.
- Mechanical equipment curbs have been set on roof.
- Continue overhead mechanical, electrical, and plumbing rough-ins over gym and locker room areas.
- Metal stud framing for gym exterior parapet walls and overhang are 90% complete.
- Interior “non” load bearing CMU block walls in locker rooms are 50% complete.
Zone “D”
- Structural steel joists and decks in the kitchen/cafeteria area are approximately 95% complete.
- Mechanical equipment curbs over kitchen have been set on roof.
- Continue installation of overhead mechanical, electrical, and plumbing rough-ins in the kitchen area.
- Equipment pads for mechanical equipment have been placed in the main mechanical and electrical room.
- Second and third floor structural joists and decks are complete.
- Overhead Mechanical, Electrical, and Plumbing, i.e. “MEP” rough-ins have begun.
- Exterior wall layout has begun.
- Area D low roofing work anticipated to start September 8th, 2025.
- Prep, Reinforce, and Place, i.e., “PRP” slab on metal decks 2nd and 3rd floor classroom wing anticipated to begin September 8, 2025.
Zone “B”
- Begin structural steel erection in the classroom wing.
- Structural steel erection in classroom wing approximately 25% complete.
- All non-load bearing CMU block walls are complete.
Zone “A”
- All non-load bearing CMU block walls are complete.
- Hollow metal door jams have been placed for CTE labs/learning spaces.
Field House
- Structural slabs are 100% complete.
Utilities
- Storm water installations have been completed up to 30th street and are ready to turn into the jobsite. Storm water piping on-site is approximately 10% complete.
- Water: Newport News Waterworks currently reviewing design drawings for compliance with their criteria and coordinating with MEB Contractors.
- Electrical – Dominion Energy transformer date has been established as October 31, 2025, the latest day transformer can arrive on-site without impacts to schedule.
- Gas: Gas meter locations have been provided to the owner and confirmed by the design team. City of Newport News has submitted a work order and application to Virginia Natural Gas.
- Communications: The contractor communicated the school will be ready for the communications subcontractor to perform their work.
Overall Completion
- Overall Completion is 32% complete.
Huntington Construction Project
Architect: Quinn Evans
Contractor: MEB General Contractors
Projected Timeline:
-
March 1, 2024
Advertise Project -
April 12, 2024
Bid Opening -
May 20, 2024
Notice of Intent to Award -
August 22, 2024
Building Permit for Construction -
September 5, 2024
Groundbreaking Ceremony, 9 a.m. -
February 3, 2026
Substantial Completion -
April 5, 2026
School Site and Building Completion -
June 4, 2026
Final Completion
More Information
Construction Progress Report Archive
- September 2025 Construction Update
- August 2025 Construction Update
- July 2025 Construction Update
- June 2025 Construction Update
- May 2025 Construction Update
- April 2025 Construction Update
- March 2025 Construction Update
- February 2025 Construction Update
- January 2025 Construction Update
- December 2024 Construction Update
- November 2024 Construction Update
- October 2024 Construction Update