Huntington Middle School: The Next Chapter
The proud history of Huntington High School and Huntington Middle School will continue with the construction of a new 600-student middle school, anticipated to open during the second semester of the 2025-2026 school year.
The new middle school is part of the city’s Southeast Community Resource Area that is set to include a public library and community center, as well as sports and recreation features.
Construction Progress Update
December 17, 2024
The Huntington Middle School building site is divided into four (4) building zones, A, B, C, & D. MEB General Contractors, Inc, the Contractor, is developing the building pad in the order of zones C, D, B, and A. The work completed in these building zones are as follows:
In Zone "C" the contractor has completed the following:
- Form, Reinforce & Place Footings 50% Complete.
- Form, Reinforce & Place Footings for the gym are complete.
- Install 1st Floor under slab plumbing & electrical, 50% Complete.
- Install 1st Floor under slab plumbing & electrical for the gym is 75% Complete
- Install Masonry Block to Finish Floor Elevation, 50% Complete.
- Install Masonry Block to Finish Floor Elevation for the gym is complete.
- Install Electrical Conduits in Masonry Block, 50% Complete.
- Masonry Block Walls installed Above Finish Floor (A.F.F.) for the gym are approximately 80% complete.
In Zone "D" of the building the contractor has completed the following:
- Form, Reinforce & Place Footings 50% Complete.
- Install Masonry Block to Finish Floor Elevation, 25% Complete.
- Install Electrical Conduits in Masonry Block, 25% Complete.
In Zone "B" of the building the contractor has completed the following:
- Excavate for Footings 50% Complete.
- Excavate for Elevator Pit, 100% Complete.
In Zone "A" of the building the contractor has completed the following:
- Excavate for Footings 50% Complete.
Utility status is as follows:
- Water: The city has paid fees and turned plans over to Newport News Waterworks to develop water utilities to the jobsite.
- Sewer: The Contractor per Change Order #2 has paid HRSD tap fees.
- Stormwater: Right-of-Way issues have been resolved along Wickham to allow the Contractor to submit permit applications for construction.
- Power: Dominion Energy is conducting an electrical survey for the site and has assigned an electrical designer to develop the service.
- Gas: City of Newport News has initiated paperwork with Natural Gas for service.
- Communications: The Civil Engineer of Record, Kimley Horn, is making design revisions to establish the most efficient route for fiber optics and Cox Communications.
Four Week Look Ahead Schedule is as follows:
- The Contractor will continue to develop the building footings along the perimeter, and rough-in for plumbing and electrical under slab and within masonry foundation block walls in building zones C, D, B & A.
- Continue to develop the elevator pit foundation in zone B.
- Continue to design and obtain permits for utilities.
Huntington Construction Project
Architect: Quinn Evans
Contractor: MEB General Contractors
Projected Timeline:
-
March 1, 2024
Advertise Project -
April 12, 2024
Bid Opening -
May 20, 2024
Notice of Intent to Award -
September 5, 2024
Groundbreaking Ceremony, 9 a.m. -
February 3, 2026
Substantial Completion -
April 5, 2026
School Site and Building Completion -
May 5, 2026
Recreation Center Substantial Completion -
June 4, 2026
Final Completion